Municipal Facility - Joint City Hall/PD Complex

Kaufman City Hall [front door cam] B06

Estimated Completion Date - August, 2018

6/5/2018:

SITEWORK

  • Plaza concrete - 100%
  • Fencing - 100%
  • Final grading - 100%
  • Irrigation - 90%

BUILDING

  • Metal panels - complete
  • Windows - 99%
  • Millwork - 95%
  • Countertops - 99%
  • Terrazzo - complete, less base
  • Final paint - 95%
  • Carpet - 90%
  • Plumbing fixtures - 90%
  • Electrical fixtures - 95%
  • Window treatments - complete
  • AV final connection - 10%
  • Install lockers - 80%
  • install canopies - 60%

SAFETY

  • No accidents to report
  • No incidents to report

LOST DAYS

  • No lost days to report.

SCHEDULE REVIEW

  • Plaza sand blasting
  • Install terrazzo base
  • Install toilet partitions & accessories
  • Complete millwork
  • Complete plumbing fixtures
  • Complete electrical trim out
  • Complete windows
  • Complete irrigation
  • Install fence operators
  • Start landscape

5-22-18

2018.05_01